Have two consecutive programmed fills ever been achieved?
Have two consecutive programmed fills ever been achieved?
Over the time I've been looking at the LHC performing, I've never seen it once manage two programmed fills in succession since a fault usually dumps the beam anyway.
Has it ever managed two consecutive programmed fills?
What is the current optimum fill time given the current turnaround time?
Has it ever managed two consecutive programmed fills?
What is the current optimum fill time given the current turnaround time?
- DCWhitworth
- LHCPortal Guru
- Posts: 599
- Joined: Mon Nov 30, 2009 8:13 am
- Location: Norwich, UK
Re: Have two consecutive programmed fills ever been achieved
The answer to the first is definitely yes.
DC
The LHC - One ring to rule them all !
The LHC - One ring to rule them all !
Re: Have two consecutive programmed fills ever been achieved
Can you give a date?DCWhitworth wrote:The answer to the first is definitely yes.
I'd be interested in looking at the meeting notes to see what they had to say about this.
Re: Have two consecutive programmed fills ever been achieved
I believe you mean consecutive physics fills ending with programmed dump - because almost all MD fills ended with programmed dump even this year and there were quite a few consecutive ones too.
And of course there were many such ones last year and maybe some this year too. There were also some calculations in one of last year's presentations about how long is an optimum run length to deliver maximum luminosity with cycling delays and beam degradation taken into account. But I don't remember what date was it and also many parameters changed since then so I doubt results from then can be applied today.
And of course there were many such ones last year and maybe some this year too. There were also some calculations in one of last year's presentations about how long is an optimum run length to deliver maximum luminosity with cycling delays and beam degradation taken into account. But I don't remember what date was it and also many parameters changed since then so I doubt results from then can be applied today.
- DCWhitworth
- LHCPortal Guru
- Posts: 599
- Joined: Mon Nov 30, 2009 8:13 am
- Location: Norwich, UK
Re: Have two consecutive programmed fills ever been achieved
Sorry, I don't recall dates but neither to I remember it being especially commented upon.jmc2000 wrote:Can you give a date?DCWhitworth wrote:The answer to the first is definitely yes.
I'd be interested in looking at the meeting notes to see what they had to say about this.
DC
The LHC - One ring to rule them all !
The LHC - One ring to rule them all !
-
- LHCPortal Guru
- Posts: 314
- Joined: Sat Nov 28, 2009 10:22 pm
- Location: Mississauga, Ontario. Canada
Re: Have two consecutive programmed fills ever been achieved
The Boffins at CERN have anticipated your curiosity and provided a statistics page and an efficiency pie chart showing the time spent in various phases of operation and set up here: http://lhc-statistics.web.cern.ch/LHC-S ... index.html
- tswsl1989
- LHCPortal Guru
- Posts: 166
- Joined: Thu Dec 24, 2009 2:22 pm
- Location: Swansea, Wales, UK
- Contact:
Re: Have two consecutive programmed fills ever been achieved
Nice link Harbles, I don't think I've seen that one before
-
- LHCPortal Guru
- Posts: 314
- Joined: Sat Nov 28, 2009 10:22 pm
- Location: Mississauga, Ontario. Canada
Re: Have two consecutive programmed fills ever been achieved
It's fairly new a few months I think. Comes from the Commissioning home page which is a handy source of info. http://lhc-commissioning.web.cern.ch/lhc-commissioning/
Re: Have two consecutive programmed fills ever been achieved
Crossing fingers seems that fill #1900 and #1901 will do that. Fill #1900 ended up with Programmed Dump, and #1901 is on its way.
- DCWhitworth
- LHCPortal Guru
- Posts: 599
- Joined: Mon Nov 30, 2009 8:13 am
- Location: Norwich, UK
Re: Have two consecutive programmed fills ever been achieved
Dumped - two out of twoferar wrote:Crossing fingers seems that fill #1900 and #1901 will do that. Fill #1900 ended up with Programmed Dump, and #1901 is on its way.
DC
The LHC - One ring to rule them all !