They published it July 31 but I've just found it now.
https://espace.cern.ch/be-dep/BEDepartm ... e_v1.1.pdf
Protons till xmas break start recommissioning at the end of Jan 2013 then heavy ions till the end of the 1st week in march then a few weeks of quench and powering tests then into long stop one till at least the end of 2013. I imagine they will need to see how things go with the buss bar splice work and other tasks before they can estimate when they will be back up and running in 2014.
2013 Schedule (Draft)
- DCWhitworth
- LHCPortal Guru
- Posts: 599
- Joined: Mon Nov 30, 2009 8:13 am
- Location: Norwich, UK
Re: 2013 Schedule (Draft)
Thanks Harbles, only just noticed this. Probably not the most challenging schedule to put together