Page 1 of 7

2012 Events Discussion

Posted: Fri Feb 17, 2012 2:48 pm
by Xymox
Hi,
Could you please add a new "Announcements"
named: "2012 Events Discussion"
So we can start adding our comments for this year?

rudolfst
Yes I can.

Should be a fun year with a nice high collision energy.

Re: 2012 Events Discussion

Posted: Fri Feb 17, 2012 3:08 pm
by CharmQuark
It's gonna be an interesting year that is for sure :ugeek:

Re: 2012 Events Discussion

Posted: Fri Feb 17, 2012 3:15 pm
by rudolfst
We are beginning to see more and more green on the Cryogenics page.

But when I look on the page with the "Cooldown status", I have noticed that in Point 4 the magnets for the RF cavities are still at room temperature (300K).

Does anybody know why they haven't started yet to cool them down?

Re: 2012 Events Discussion

Posted: Tue Feb 21, 2012 2:42 am
by Harbles
Hi Rudolfist, my guess would be that they are still weeks away from beam and the RF cavities cool relatively quickly. Right now they are doing current testing on the magnets in the green sectors.

Re: 2012 Events Discussion

Posted: Wed Feb 22, 2012 5:57 pm
by Harbles
And today we see them starting to fill and chill the RF at L4.

Re: 2012 Events Discussion

Posted: Thu Mar 01, 2012 3:19 am
by JNW
I just looked at the cryo page, and at the moment it's all green. :mrgreen:

Re: 2012 Events Discussion

Posted: Thu Mar 01, 2012 5:39 am
by DCWhitworth
JNW wrote:I just looked at the cryo page, and at the moment it's all green. :mrgreen:
That's cool 8-)

Re: 2012 Events Discussion

Posted: Thu Mar 01, 2012 5:52 am
by chriwi
Thats the best way to put it DC.

Or even shorter:


It's cool !!!

Re: 2012 Events Discussion

Posted: Mon Mar 05, 2012 10:48 am
by DCWhitworth
Whoo hoo ! Page 1 reports - "Technical Stop finished - HW commissioning on-going"

Collider mode is now - "Machine Checkout: No Beam"

The Beast awakens . . . .

Re: 2012 Events Discussion

Posted: Wed Mar 07, 2012 2:01 am
by RocketManKSC
[img]
cernstart.JPG
cernstart.JPG (30.08 KiB) Viewed 43096 times
[/img] Looks like they are starting to ramp things up

Re: 2012 Events Discussion

Posted: Wed Mar 07, 2012 3:15 pm
by chriwi
but most likely only ramping magnets without beam or why is there no beam intensity visible?
Would make sence to try the magnets first without beam evenso the unit TeV would be missleading, probably they only mean the magnetstrength the later have to use for the mentioned beamenergy (TeV).

Re: 2012 Events Discussion

Posted: Wed Mar 07, 2012 3:37 pm
by DCWhitworth
chriwi wrote:but most likely only ramping magnets without beam or why is there no beam intensity visible?
Would make sence to try the magnets first without beam evenso the unit TeV would be missleading, probably they only mean the magnetstrength the later have to use for the mentioned beamenergy (TeV).
Definitely no beam in the machine, page 1 clearly says so.

Re: 2012 Events Discussion

Posted: Fri Mar 09, 2012 10:20 pm
by DCWhitworth
Machine closed, test ramp to 4TeV :)

Re: 2012 Events Discussion

Posted: Sat Mar 10, 2012 4:00 pm
by CharmQuark
Good times! :D

Re: 2012 Events Discussion

Posted: Mon Mar 12, 2012 6:08 am
by chriwi
"Saturday 10th Mar 10:30 Beam to TI8 downstream TED."

Looks like they are not far from a circular beam now again.