 Post subject: Re: 2017 Operation
 Post Posted: Thu May 18, 2017 10:42 pm 
Offline

Joined: Sat Oct 03, 2015 7:58 pm
Posts: 131
Fixed, beam is back.


Top 
 Profile  
 
 Post subject: Re: 2017 Operation
 Post Posted: Sat May 20, 2017 12:02 am 
Offline

Joined: Sat Oct 03, 2015 7:58 pm
Posts: 131
A bit behind schedule due to the water leak - still no bunch trains, but other tests got done. Stable beams potentially Sunday afternoon/night.


Top 
 Profile  
 
 Post subject: Re: 2017 Operation
 Post Posted: Sat May 20, 2017 4:56 pm 
Offline

Joined: Sat Oct 03, 2015 7:58 pm
Posts: 131
First bunch trains in the machine, 4 times 12 bunches per beam.

Attachment:
bunchtrains.png
bunchtrains.png [ 88.62 KiB | Viewed 77 times ]


Top 
 Profile  
 
 Post subject: Re: 2017 Operation
 Post Posted: Tue May 23, 2017 2:40 pm 
Offline

Joined: Sat Oct 03, 2015 7:58 pm
Posts: 131
First stable beams of 2017.

The number of collisions per bunch is already close to the 2016 records. Scaled up to 2800 bunches we could get 170% the design luminosity.

Attachment:
stablebeams.png
stablebeams.png [ 96.49 KiB | Viewed 45 times ]


Top 
 Profile  
 
Display posts from previous:  Sort by  
 
Post new topic Reply to topic  [ 19 posts ]  Go to page Previous  1, 2

Board index » General topics » The Accelerator


Who is online

Users browsing this forum: No registered users and 1 guest

 
 

 
You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot post attachments in this forum

Search for:
Jump to:  
cron